It's the end of the week, and we're making great progress. Many of the students stayed after this week with Mr. Bergen and finished making the long roadbed sections. Today and tomorrow we will be finishing up the roadbeds. It is expected that by the end of next week the bridge will be completed and ready for Mr. Bergen to walk across. To accomplish this goal, both classes are going to need to work extremely hard, including staying after school next week. Unfortunately, we still need to make time to rip down the wonderful bridge that we worked so hard on. That's okay though because for some people, ripping it down is half the fun! More to come next week (with more pictures too)!
Thursday, June 5, 2008
Tuesday, June 3, 2008
Week Six
Friday, May 30, 2008
Week Five (continued)
Wednesday, May 28, 2008
Week Five
Friday, May 23, 2008
Week Four

On Thursday, we started making the pads. The pads are at the end of the bridge where the roadbed connects, almost like a support system, so clearly the pads are extremely important. To make them, we had to dig holes and then fill them with concrete. Unfortunately, on Thursday, we ran out of concrete, so we had to stop there, but that didn't stop us for long. On Friday, a team of eight kids went out and continued making and pouring cement as the rest of us constucted the initial frame for the roadbed. In case you were wondering, the roadbed is what hangs from the towers and is what Mr. Bergen has to walk across once we finish construction.
Monday, May 19, 2008
Week Three
Thursday, May 15, 2008
Week Two
Subscribe to:
Posts (Atom)